UPDATE 06/18/2021:

Builders completed all paving today for the 2021 Road Program. Builders will be back next week to do general site cleanup. Striping is scheduled for next week. Completion of landscaping restoration will continue to be delayed until drought conditions improve.

Please let me know if you have any comments questions.

Thanks and have a good weekend,

Doug

Doug Keppy, P.E.

Senior Project Engineer

Engineering Enterprises, Inc.

52 Wheeler Road

Sugar Grove, IL  60554

T: (630) 466-6700  F: (630) 466-6701

www.eeiweb.com

dkeppy@eeiweb.com

 

UPDATE 06/17/2021:

Builders started the surface course for the paving project today.  They intend to complete all the paving today and tomorrow.

UPDATE 06/09/2021:

Builders started and completed all leveling binder paving operations for the MFT program today. Builders intends on paving the surface course next Tuesday June 15th. With the current drought and heat conditions, coordination is ongoing regarding restoration efforts.

Please let me know if you have any questions.

Thanks,

Doug

Doug Keppy, P.E.

Senior Project Engineer

Engineering Enterprises, Inc.

52 Wheeler Road

Sugar Grove, IL  60554

T: (630) 466-6700  F: (630) 466-6701

www.eeiweb.com

dkeppy@eeiweb.com

 

UPDATE 06/08/2021:

Builders had a crew on site yesterday that prepared butt joints, asphalt edgework, site cleanup and sweeping, and installation of “No Parking” signs in preparation for paving this week.

Due to weather, paving has been pushed to tomorrow 06/09/2021 and restoration has been pushed to the end of the week. The project should be finished the next week.

Please let me know if you have any questions.

Thanks,

Doug

Doug Keppy, P.E.

Senior Project Engineer

Engineering Enterprises, Inc.

52 Wheeler Road

Sugar Grove, IL  60554

T: (630) 466-6700  F: (630) 466-6701

www.eeiweb.com

dkeppy@eeiweb.com

 

UPDATE 06/03/2021:

Builders had a milling crew on site today that completed the asphalt removal within the project limits.  D’Land also had a crew show up near the end of the day to clean up the project.

Builders will be on site tomorrow removing butt joints and preparing for paving next week. Paving is still scheduled for Tuesday next week and restoration is still scheduled for Monday. The project should be finished the following week.

Please let me know if you have any questions.

Thank you,

Doug

Doug Keppy, P.E.

Senior Project Engineer

Engineering Enterprises, Inc.

52 Wheeler Road

Sugar Grove, IL  60554

T: (630) 466-6700  F: (630) 466-6701

www.eeiweb.com

dkeppy@eeiweb.com

UPDATE 06/02/2021:

Builders had a milling crew on site today that completed the asphalt removal on Park Avenue between Division and IL 47 and between IL 47 and Capitol Drive. They also began some of the asphalt removal on Park Avenue between Capitol Drive and St. James Parkway.

Builders will continue to mill tomorrow and should be complete with asphalt removal by the end of the day. Paving is still scheduled for Tuesday next week and restoration is now scheduled for Monday.

Please let me know if you have any questions.

Thank you,

Doug

Doug Keppy, P.E.

Senior Project Engineer

Engineering Enterprises, Inc.

52 Wheeler Road

Sugar Grove, IL  60554

T: (630) 466-6700  F: (630) 466-6701

www.eeiweb.com

dkeppy@eeiweb.comUPDATE 06/01/2021:

D’Land had two crews on site today. One crew completed the remaining concrete work for the project while another crew cleaned up construction debris around the project area. Builders had a crew on site today which completed hot-mix asphalt path and driveway repairs.

Builders will be on site the next couple days completing the asphalt milling operations for the project. It is anticipated that paving will begin next Tuesday and be completed next week. Restoration operations are to occur this week.

Please let me know if you have any questions.

Thank you,

Doug

Doug Keppy, P.E.

Senior Project Engineer

Engineering Enterprises, Inc.

52 Wheeler Road

Sugar Grove, IL  60554

T: (630) 466-6700  F: (630) 466-6701

www.eeiweb.com

dkeppy@eeiweb.com

 

UPDATE 05/27/2021:

D’Land had two crews on site today. One crew was forming and performing structure adjustments while another crew poured sidewalk along Capital and Park. Nearly all project concrete work was poured, but rain caused a delay. D’Land will complete all remaining project concrete work tomorrow morning, weather pending.

Builders intends on beginning asphalt operations mid next week

Please let me know if you have any questions.

Thanks,

Doug

Doug Keppy, P.E.

Senior Project Engineer

Engineering Enterprises, Inc.

52 Wheeler Road

Sugar Grove, IL  60554

T: (630) 466-6700  F: (630) 466-6701

www.eeiweb.com

dkeppy@eeiweb.com

 

 

UPDATE 05/25/2021:

D’Land was on site today and stripped all forms from concrete poured yesterday. D’Land continued forming and will be complete with forming and structure adjustments tomorrow. Concrete pouring will occur tomorrow and Thursday, which should conclude all concrete work within the project area.

Please let me know if you have any questions or concerns.

Thanks,

Doug

Doug Keppy, P.E. Senior Project Engineer

Engineering Enterprises, Inc.

52 Wheeler Road

Sugar Grove, IL  60554

T: (630) 466-6700  F: (630) 466-6701

www.eeiweb.com

dkeppy@eeiweb.com

 

UPDATE 05/24/2021:

D’Land had two crews on site today. One crew was forming while another crew poured a majority of the curb and gutter throughout the project area. D’Land will be on site tomorrow to adjust structures, strip forms of concrete items poured today, and continue forming. D’Land intends on pouring Wednesday and should be nearly complete by the end of day.

Builders will not be performing any asphalt work this week, and an updated schedule will be sent once received. There is a possibility restoration could occur at the end of this week or next week. Please let me know if you have any questions.

Thanks,

Doug

Doug Keppy, P.E.

Senior Project Engineer

Engineering Enterprises, Inc.

52 Wheeler Road

Sugar Grove, IL  60554

T: (630) 466-6700  F: (630) 466-6701

www.eeiweb.com

dkeppy@eeiweb.com

UPDATE 05/21/2021:

D’Land was on site today performing demolition and formwork for concrete. The demolition crew completed all removals west of 47 and they are now complete. D’Land forming crew formed a majority of sidewalk and curb east of 47 and will pour at 7 AM Monday, weather pending.

Concrete pouring will continue through at least end of day Tuesday. Builders Asphalt may begin milling operations of the roadways Wednesday or Thursday next week, but more than likely will hold off until after the holiday weekend. Please let me know if you have any questions.

Doug

Doug Keppy, P.E.

Senior Project Engineer

Engineering Enterprises, Inc.

52 Wheeler Road

Sugar Grove, IL  60554

T: (630) 466-6700  F: (630) 466-6701

www.eeiweb.com

dkeppy@eeiweb.com

 

UPDATE 05/20/2021:

Yesterday, May 19th a demolition crew from D’Land removed sidewalk along Capital north of Park Avenue before they were called off due to weather.

Today, a demolition crew from D’Land removed all concrete items east of IL 47 within the project area. D’Land will complete removals of concrete items tomorrow.

Additionally, a forming crew from D’Land was on site today forming curbs and sidewalk along Capital Drive. Formwork will continue tomorrow, with concrete pouring to begin Monday May 24th.

If you have any questions or comments, please let me know.

Thank you,

Doug

Doug Keppy, P.E.

Senior Project Engineer

Engineering Enterprises, Inc.

52 Wheeler Road

Sugar Grove, IL  60554

T: (630) 466-6700  F: (630) 466-6701

www.eeiweb.com

dkeppy@eeiweb.com

 

UPDATE 05/18/2021:

A demolition crew from D’Land was on site today and removed concrete curb and gutter and sidewalk adjacent to the intersection of Park and Capital as well as Capital Drive south of Park Avenue. D’Land will continue to remove items tomorrow and there is a possibility that form work will begin tomorrow as well in areas where concrete items have already been removed. Proper notification has been given to all residents and businesses to be impacted by concrete construction activities.

Builders was on site at Norris Road and completed all patching work at that location.

If you have any questions or comments, please let me know.

Thank you,

Doug

Doug Keppy, P.E.

Senior Project Engineer

Engineering Enterprises, Inc.

52 Wheeler Road

Sugar Grove, IL  60554

T: (630) 466-6700  F: (630) 466-6701

www.eeiweb.com

dkeppy@eeiweb.com

 

UPDATE 05/17/2021:

A demolition crew from D’Land was on site today and removed concrete curb and gutter and sidewalk along the west side of Park Avenue from the northeast corner of IL 47 to the Northwest corner of Park and Capital. D’Land will continue to remove items tomorrow and there is a possibility that form work will begin tomorrow as well in areas where concrete items have already been removed. The contractor has been informed not to remove items that will impact access to residential or business drives until proper notification (i.e. paper notices on lathes) has been given to those impacted.

Builders Paving will be starting the patch work along Norris Road tomorrow, weather pending.

If you have any questions or comments, please let me know.

Thank you,

Doug

Doug Keppy, P.E.

Senior Project Engineer

Engineering Enterprises, Inc.

52 Wheeler Road

Sugar Grove, IL  60554

T: (630) 466-6700  F: (630) 466-6701

www.eeiweb.com

dkeppy@eeiweb.com

UPDATE 05/13/2021:

The concrete contractor will be on-site tomorrow 05/14/2021 to begin saw-cutting on Capital Drive and Park Avenue. On Monday, they will continue sawcutting and possibly begin to remove concrete.  In addition, on Monday, the Contractor will be on-site to patch on Norris Road.

UPDATE 05/05/2021:

The 2021 Village Road program is scheduled to begin the week of May 10, 2021. The Village’s annual Program is funded by the state allocated Motor Fuel Tax (MFT) and the local Road Infrastructure Fee (RIF). In an effort to best utilize the available funds, the Program focuses on Resurfacing and Preventative Maintenance. This year’s program includes:

  • Resurfacing Capital Drive from Bliss Road to Galena Boulevard;
  • Resurfacing Park Avenue from IL RT47 to St. James Parkway in the Windsor Point subdivision;
  • Patching on Norris Road within the Village limits; and
  • Crack sealing on various streets including Denny Road, Division Street, Ke-De-Ka Road, Carriage Hill Lane & Court, and the Hannaford Farm and Settler’s Ridge subdivisions.

Affected areas should have already received a notice of sidewalk and curb repairs. As requested, please move any vehicle that you intend to use out of your driveway by 6:00 A.M. until the work is complete.

During the replacement and concrete curing time, vehicles will not have access to your driveway for five days after the concrete has been poured and we ask that no traffic drive on the new sidewalk or curb during this time. At the end of the five days, the barricades will be removed and you will have full access back to your driveway.

If your asphalt driveway is damaged during the removal operation, the Contractor will repair your driveway when all concrete work is completed in your area.

If you have any questions or special access needs, please call the field engineer, Doug Keppy of Engineering Enterprises, Inc. at 815-257-8970 or Village of Sugar Grove Public Works at 630-391-7230.

We are sorry for this inconvenience and we thank you for your cooperation.

To view the overall 2021 Road Program Map and individual neighborhood project maps, click here.