Illinois Tollway I-88 Crossroad and Bridge Work

Contractors are expected to start work on April 2nd at the Somonauk Rd and Keslinger Rd bridges  followed by the Bliss Rd bridge on April 9th.  Additionally, the WB I-88 entrance ramp from Annie Glidden Rd will close on April 2nd with a detour provided. Tentative time-frames are also listed for the other bridges/ramp work along with their impacts to local traffic (i.e. full closures, detours, etc.).  If you have any questions, please contact myself or you can find more information at www.illinoistollway.com, click on Explore Projects.

The Illinois Tollway is resurfacing 37 miles of the Reagan Memorial Tollway (I-88), between Illinois Route 251 in Rochelle and Illinois Route 56 in Sugar Grove, to provide a smoother riding surface for the traveling public. The project also includes repairs to local crossroad bridges, ramps at various interchanges and the DeKalb Oasis, construction of new crash investigation sites, as well as guardrail, median, drainage, landscaping and lighting improvements.

Read More information from IDOT

https://www.illinoistollway.com/projects/reagan/roadway-resurfacing-bridge-repairs

Crossroad Bridge over I-88

(Type of Closure or Traffic Impacts)

Anticipated Closing or

Lane Reduction

Anticipated Openings
Main Street

(Full Closure – No Detour)

Mid-June, 2018 Late June, 2018
IL Route 251 Ramps

(Full Closures – Max of 5 Days Each –

Non-Concurrently – Detours Provided – Coordinated with I-39 Ramp Work)

Anticipated Commencement Late April, 2018 Anticipated Completion

Late May, 2018

Caron Road

(Off-Peak Daytime Lane Closures)

Spring, 2018 Fall, 2019
I-39 Ramps to/from I-88

(Full Closures – Max of 3 Days Each –

Non-Concurrently – Detours Provided – Coordinated with IL 251 Ramp Work)

Anticipated Commencement Late April, 2018 Anticipated Completion

Late May, 2018

Mulford Road

(Full Closure – No Detour)

Mid-July, 2018 Late August, 2018
Locust Road

(Full Closure – No Detour)

Mid-June, 2018 Mid-July, 2018
Woodlawn Road

(Full Closure – No Detour)

Mid-July, 2018 Late July, 2018
Tower Road

(Full Closure – No Detour)

Late July, 2018 Late August, 2018
Willrett Road

(Full Closure – No Detour)

Late August, 2018 Late September, 2018
Shabbona Road

(Daily Lane Closures with Flaggers)

Mid-July, 2018 Early August, 2018
University Road

(Full Closure – Detour Provided)

Early August, 2018 Late August, 2018
Annie Glidden Road & Ramps

(Full Closures – Detours Provided – Coordinated with Peace Rd Ramp Work)

April 2, 2018 August, 2018
Annie Glidden Rd Ramp A

(WB I-88 Entrance Ramp)

April 2, 2018 May 10, 2018
Annie Glidden Rd Ramp B

(WB I-88 Exit Ramp)

May 14, 2018 July 2, 2018
Annie Glidden Rd Ramp C

(EB I-88 Entrance Ramp)

May 14, 2018 August 6, 2018
Annie Glidden Rd Ramp D

(EB I-88 Exit Ramp)

May 14, 2018 August 6, 2018
South First Street

(Full Closure – Detour Provided)

Spring, 2019 Summer, 2019
4th Street (IL 23)

(Off-Peak Daytime Lane Closures)

August, 2018 October, 2018
Peace Road

(Ramp Closures – Staged Construction w/

NB closure – Detours Provided – Coordinated with Annie Glidden Rd work)

Early July, 2018 Late August, 2018
Somonauk Road

(Single Lane Configuration w/

Temp Traffic Signals)

April 2, 2018 Mid-July, 2018
Hinckley Road

(Full Closure – No Detour)

Early July, 2018 Late September, 2018
Keslinger Road

(Full Closure – No Detour)

April 2, 2018 Mid-July, 2018
County Line Road

(Single Lane Each Direction Maintained)

Late September, 2018 Mid-November, 2018
Watson Road

(Full Closure – No Detour)

Mid-May, 2018 Early July, 2018
Dauberman Road

(Full Closure – No Detour)

Early August, 2018 Late September, 2018
Main Street

(Daily Lane Closures with Flaggers)

Early June, 2018 Early July, 2018
Bliss Road

(Single Lane Configuration w/

Temp Traffic Signals)

April 9, 2018 Mid-July, 2018
IL 56 Ramps to/from I-88

(Single Lane Configuration)

Spring, 2019 Summer, 2019